* 4.7 Translate f-r-n for beta Sep 6 to Sep 26 21d
This seems not consistent with f-12-trans-tasks, which says Sep 9 to
Sep 18.
While I stuck with John's dates for the releases, I tried to maximize
the time L10N had available. I wonder whether 9 days is sufficient. I
would expect this cycle that the beta would be the bulk of the release
notes (although I suppose that remains to be seen).
* 4.8 Build f-r-n.rpm for beta Sep 29
A question, there is 2 days blank between 4.7 and 4.8. What is this for?
No good reason
* 6.7 Translate f-r-n for GA Oct 20 to Oct 26 7d
This seems not consistent with f-12-trans-tasks, which says Oct 9 to
Oct 16.
The later we can do this the better. Release notes seem to be the last
thing on people's radar, and we tend to discover important changes late,
so the later we can make the POTs the better. Also, the original
schedule had some Docs tasks out of order.
* Review translation not scheduled
Please set up 'Review translation'. Since we translate PO file, so it
is extremely helpful if docs team can build html for review before the
deadline.
That is a really excellent catch. I think we need to work on the
mechanics of this, but it could have a number of advantages.
* 7.4 Translate 0-day
I understand that docs team has little window for Zero Day Update. But
let me become devil this time as experiment. Is any chance that
rel-note team can place this entry before GA Public Availability 3-Nov
for inclusion? Just tiny window is fine. I can not guarantee at all
how many translators can respond.
My expectation was that on release day the 0-day changes would be
available in English only, with an update rpm to follow the release.
However, we are still discussing whether it makes sense to have a single
rpm with six documents in 41 languages, so that may change. It might
make more sense to delay the availability of the update rpm rather than
try to push the POT creation earlier, thus missing late breaking
changes. On the other end, we are going to try to be more proactive in
hounding the developers for release notes input, so maybe we can reduce
the number of those late changes.